January 8, 2020

Starting January 1, 2020, we have hired a new/ old landscape company to assist us with all our landscape needs including mowing, trimming and bush removal/replacement. Our new company just happens to be our former landscape provider Ameriscape. With the many problems i...

October 20, 2019

Two storm sewers were repaired due to failing structure and deterioration to ground. Contractor made needed repairs to structure and completed repairs to landscaping.

October 20, 2019

We have completed the installation of a concrete pad and walk for the new storage building expected in early 2019. Pad was installed for a 14' x 20' building to house pool furniture, golf cart and miscellaneous items stored in equipment room at this time. A gate will b...

October 20, 2019

The 2019 landscape bush removals and replacement project is almost complete. We are currently waiting on a back order of bushes to be replaced and project will be completed for 2019.

April 23, 2019

We have met with contractor to do some repairs to our roads. After repairs and some crack sealing, contractors will schedule or roads for asphalt sealant. Roads and drives will be sectioned off as we have done in the past. We will send out notices to everyone when sche...

April 23, 2019

We are currently getting bids for a contractor to inspect and seal all roof vents and chimney caps. The work should take place within the next couple of weeks. Please report any water intrusions to your unit to Rick or Board Member when it occurs so we can take care of...

April 23, 2019

Our mowing season will begin on April, 25th. Some areas are saturated with all the rain and may be skipped to eliminate any damages. Remember to contact Rick for concerns. Any issues will require an issue form to be filled out and returned to Rick or Board Member.

We wi...

July 30, 2018

Construction repairs on all units are going very well. The contractors are ahead of schedule and our timeline for completion should be the end of September. There are many separate crews working on several buildings at a time including caulking crews and painting crews...

July 30, 2018

Road repairs throughout the community will be scheduled sometime in late September. An inspection on all asphalt surfaces will be done prior to contractor's bid.  Procedures for repairs will consist of grinding out bad areas at a depth of 2 1/2" and repairing with new...

July 30, 2018

As you know we have been very aggressive with our landscape needs this year. We have cut down and removed many bushes from patio areas and near buildings. We will continue with removals and replacements the beginning of September. Many bushes still remaining near build...