Our landscape contractors are scheduled for tomorrow, Wednesday, Oct. 14th to install bushes and trees. If you have new bushes or trees installed and you can water them, let us know or we will need to make other arrangements.
New sidewalk and wheel chair ramp completed. Thank you Jim Antonio for your assistance with putting in 4 cu.yds of mulch. Looks great and much needed.
New concrete handicap ramp and pad at pool entrance is completed. New railing and gate will be installed in a few weeks.
Construction on our new pool entrance will start on September 21st. A new larger pad will be installed with wheelchair accessibility. Later a new railing will be installed the length of the new pad and wheelchair ramp.
We are also having a new sidewalk installed from the existing sidewalk at clubhouse entrance to the east and west roadway in front of clubhouse.